Significant Progress Made on the Construction of “LIDO House”

The new “LIDO House” complex is steadily taking shape in Imanta, Riga. Since construction began this summer, the building has undergone a remarkable transformation. Work on the roof and façade is nearing completion, and from November onwards, an increasing share of construction activities will move indoors, where the infrastructure for the new complex is being developed. Approximately 20% of the total construction work has now been completed.

All News

The reconstruction began with extensive demolition work, exposing the building’s structural framework and clearing space for new installations. More than 3,000 m³ of construction debris was removed during this phase. This figure excludes material from the old concrete floor, which was crushed into aggregate and has already been reused in the construction of the new floor foundations. By reusing some of the demolished materials directly on site, the project has reduced both construction waste and the need for new materials.

 

Following demolition, work continued on the new foundations. A total of 297 foundation piles are planned to provide stable support for the new structures. Construction of the connecting foundation elements, columns and retaining walls has also progressed. In October, preparations began for pouring the concrete slab above the ground floor of the building’s office section.

The installation of façade panels has significantly transformed the building’s exterior. The panels are gradually enclosing the previously exposed structural framework, while thermal insulation and new roofing materials are being installed on the roof. Most of the window frames have also been fitted.

Inside the building, work continues on infrastructure that will largely remain hidden once the production facility is completed. Underground drainage systems are being installed beneath the future floors, while sand and crushed stone base layers are being prepared in areas where utility installations have already been completed. In the freezer area, ground heating pipes have been installed and tested to prevent the floor foundations from freezing.

Meanwhile, work continues across the site on the installation of sewer networks, earthing systems and protective conduits for electrical cables. A rainwater drainage system is also being installed to channel water away from the building’s roof.

“LIDO House” is a major investment project aimed at expanding the company’s production capabilities, with approximately EUR 30 million earmarked for its development. The new complex will house a central kitchen, production facilities, warehouses and office space.

The building is scheduled for completion and commissioning in the final quarter of 2027, with full-scale food production expected to commence in spring 2028.